The brief
An estate that had outgrown its own drawings.
The estate had grown by acquisition over two decades. Three sites, six buildings, fire-compartmentation drawings that disagreed with one another, and a regulator that had moved the goalposts. The Trust’s Director of Estates had a Building Safety Act inspection on the diary, and a compliance picture that no single supplier had ever owned end-to-end.
They didn’t want surveyors and remediation contractors and an asset-register vendor in three separate conversations. They wanted one party to take the brief — and to hand back evidence the regulator could accept on first look.
The approach
Three phases. One workflow. One source of truth.
Phase 01 — Intrusive survey
14 weeks across all wards, plant rooms, riser shafts. Every penetration, every compartment line, every door — mapped, photographed, scored. Surveys uploaded live into Uptick as the team walked the estate, so the asset register grew in real time rather than at the back-end of the contract.
Phase 02 — Sequenced remediation
Programmed by risk register, not by ward operations. Critical-care compartments first; night shifts where the estate needed beds open. Procore tracked the as-built changes against the survey baseline, so the remediation record was the audit record.
Phase 03 — Golden-thread digitisation
Every asset on Uptick. Every survey cross-referenced. Procore for the as-built drawing pack. M365 SharePoint for the controlled-document layer. Handed over as a single compliance pack — searchable, auditable, defensible.
“They didn’t just remediate the building. They handed us a compliance posture we can defend to the regulator and to our insurers — for years, not months.” — Director of Estates and Facilities
The outcome
Audit-ready, on first inspection.
The Trust handed its compliance pack to the Building Safety Regulator pre-emptively, ahead of the first BSA inspection of the estate. The inspector accepted the pack as evidenced — and the estate passed without remedials. The compliance picture that had previously lived across three suppliers, two spreadsheets and a folder of legacy drawings, now lives in one searchable workflow that the estates team can interrogate from a phone.
Metrics
- 14,200+ assets onboarded to the live register
- 3,800 compartmentation penetrations surveyed and scored
- 11 months from kick-off to audit-ready handover
- 0 remedials at first BSA inspection
Credits
- Lead company: Gemini AMPM
- Project team: L. Woodford (Passive lead), R. Gemmel (Projects), P. Fitzpatrick (Compliance hub)
- Frameworks applied: Building Safety Act 2022, BS 9999 / BS 9991, PPN 06/20 social value
- Operating stack: Uptick (asset + maintenance), Procore (delivery), M365 SharePoint (golden thread)